Ailes Marines, a subsidiary of Iberdrola, has installed the first offshore wind turbine in Brittany.

The installation of the first of the 62 wind turbines that will equip the Saint-Brieuc wind farm was carried out on May 11 by Ailes Marines’ contractor, Siemens Gamesa Renewable Energy. The operation was carried out from the Norwegian company Fred Olsen’s jack-up vessel Brave Tern.

The first wind turbine of the Saint-Brieuc wind farm was installed on position number SB44 located on the northern part of the site. With this installation, Brittany has its first offshore wind turbine.

” This successful installation of the first offshore wind turbine at the Saint-Brieuc wind farm is a great day for Brittany and for the project. It means that we are entering the home stretch of the project, which will result in renewable and carbon-free energy production for the people of Brittany. After more than a decade of effort and commitment from the Brittany region, local stakeholders and Iberdrola teams, this first wind turbine manufactured in Le Havre and equipped in Brest is also the culmination of a great industrial adventure, of which we can be very proud,” says Emmanuel Rollin, Managing Director of Iberdrola France.

Starting point for the installation phase of the 62 wind turbines

The installation phase of the 62 wind turbines is now underway. This starting point is decisive because it is emblematic of the last phase of installation of the wind farm.

The installation ship Brave Tern will make several rotations from Le Havre in the coming months, each time carrying the components of 4 wind turbines.

The wind turbines for the Saint-Brieuc wind farm are manufactured in France, at the Siemens Gamesa Renewable Energy industrial site located in the port of Le Havre (76). On this dedicated site, about 900 jobs are mobilized for their construction and assembly.

The masts of the 62 wind turbines are pre-equipped by the company Haizea Wind on the Brest polder. This new industrial activity continues to mobilize on the site about forty jobs for the mechanical and electrical assembly of all the internal elements of the masts.

An installation in several stages 

At sea, the 90 m high wind turbine mast is first lifted from the barge and then lowered by crane onto the transition piece of the “jacket” foundation, before being attached to it. Then the nacelle is lifted and installed on the mast. Finally, the 3 blades are attached to the rotor of the nacelle.

The structure installed at sea measures 209 meters at the tip of the blade and has a rotor of 167 meters in diameter. It is designed to best respond to the wind regime that characterizes the Bay of Saint-Brieuc.

For the first wind turbine, these operations were successfully carried out by the Brave Tern, a vessel specialized in the installation of offshore wind turbines. For each rotation from Le Havre to the Saint-Brieuc wind farm site, the Brave Tern carries 4 masts, 4 nacelles and 12 blades.

Latest News

LD Armateurs Group has taken delivery of the DP2 multipurpose support vessel TVO Mariner, strengthening the Group’s fleet and expanding the offshore capabilities of its subsidiary LD TravOcean, which specialises in subsea cable installation and protection.

LD Armateurs Takes Delivery of DP2 Vessel TVO Mariner

DP2 multipurpose support vessel TVO Mariner, expands LD TravOcean’s capabilities across subsea cable, telecommunications and offshore wind projects LD Armateurs Group has taken delivery of...
PaxOcean Group, a member of Kuok Maritime Group, and Ulstein Design & Solutions AS have signed a contract for the design and construction of a new ULSTEIN SX222 Service Operation Vessel (SOV) for NYK Line (Nippon Yusen Kabushiki Kaisha).

NYK Selects ULSTEIN SX222 for New Offshore Wind SOV

PaxOcean and Ulstein join forces to deliver NYK’s next-generation offshore wind SOV PaxOcean Group, a member of Kuok Maritime Group, and Ulstein Design & Solutions...
Dutch winch specialist Dijvler is expanding into the sea-going vessel market following the acquisition of the rights, designs, drawings and certifications of C-Nautical, enabling the company to launch a new standardised range of anchor and mooring winches for cargo vessels and offshore support vessels. With nearly 50 years of experience supplying anchor and mooring winches for inland waterway vessels, Dijvler is now applying its established engineering expertise to the wider commercial marine sector. The company expects to deliver its first orders for the new programme in 2027.

Dijvler Targets Sea-Going Vessels With New Winch Range

Dutch winch specialist Dijvler, builds on nearly 50 years of inland vessel experience with a new standardised range for cargo and offshore support vessels Dutch...
Safehaven Marine has launched Ederra 8, an 18-metre Interceptor 60 pilot boat built for the MVD Pilots Association in Montevideo, Uruguay. The vessel is the third pilot boat Safehaven Marine has built for the Montevideo pilots and the fourth vessel supplied to the organisation overall. The latest delivery follows the Ederra 6 and Ederra 7, two Interceptor 48 pilot boats delivered in 2022, which have been operating successfully with the pilots over recent years.

Safehaven Marine Launches Interceptor Pilot Boat Ederra-8

Safehaven Marine has launched Ederra 8, an 18-metre Interceptor 60 pilot boat built for the MVD Pilots Association in Montevideo, Uruguay https://youtu.be/a7ImyS0Er70?si=glEf4QIrKSlrVSZk Safehaven Marine has launched...

Related news