Renewable EnergyTidal PowerAWS wave energy converter takes shape in Glasgow ahead of testing

AWS wave energy converter takes shape in Glasgow ahead of testing

Last week AWS Ocean Energy achieved a critical milestone in the construction of its 16kW Archimedes Waveswing wave energy converter when the two major sub-assemblies were joined together and the Waveswing finally took shape.  Final hook-up of the internal systems is now under way at Malin Marine in Glasgow and AWS expects to start commissioning and dry-testing early in July, before deployment at the European Marine Energy Center (EMEC) in Orkney later this year.

Simon Grey, CEO of Inverness based AWS said:

“It is brilliant to see the machine complete and you get a real feeling that it ‘looks the business’ – no arms, levers, hinges, joints and other bits to get broken by surface waves, just a simple telescopic can which will pulsate beneath the surface.  This is what wave power machines should look like.”

The prototype Waveswing is being built by Malin Marine at their fabrication facility at Westway Dock in Renfrew, Glasgow.  The £3.4million project has been funded by Wave Energy Scotland (WES) as part of the Novel Wave Energy Converter development programme.  The objective of the programme is to demonstrate Europe’s leading wave energy technologies in real sea conditions.

Weighing 50 tons, the 7 meter high, 4 meter diameter Waveswing will produce continuous power of 16kW in moderate seas.  The device is moored subsea and reacts to changes in pressure caused by passing waves.   It is moored on a single tension tether and is self-installing.  The subsea location and ability to winch low in the water-column mean that extreme storm loadings are avoided and the device can continue to operate in rough sea conditions.  Unlike other point-absorber concepts, the Waveswing reacts equally well to long ocean swell waves as to short, wind-driven seas, resulting in high energy capture per unit of submerged volume.

Complete Waveswing in Glasgow

Simon Grey said:

“Since coming a close third in the US Department of Energy Wave Energy prize we have further optimised the Waveswing and achieved a three-fold increase in energy capture.  As a result we are confident that the Waveswing really is the best prospect for practical, affordable wave power.  The whole team at AWS are looking forward to proving this for real during at-sea testing later this year”.

The design of the current generation of Waveswing has focussed on remote power applications such as driving sub-sea oilfield assets or use in oceanographic monitoring.  It’s low mooring footprint and practical design for maintenance recovery are key features which make Waveswing attractive to oil and gas operators.

The Waveswing will now undergo an intensive commissioning and dry-test programme designed to ensure that all of the sub-systems operate as required before the device makes its journey to Orkney for deployment at EMEC’s test site in Scapa Flow later in the year.

Tim Hurst, Managing Director of WES said:

“It is fantastic to see the progress that AWS has made with the development of the Waveswing over the past four years and we have been delighted to support this through the Novel Wave Energy Converter programme.  We are really looking forward to seeing the Waveswing in action later this year.”

The Waveswing development programme has been supported by a strong and predominantly Scottish team of subcontractors including 4c Engineering and Quoceant on design, Sequentec on supply of the control system, Malin for the main build and assembly work, and JGC Engineering for fabrication of the anchor frame.  International subcontractors include Trelleborg for supply of the rolling seal, and SRP Subsea for supply of the Rocksteady mooring connector.

Categories:

Latest News

MacGregor has secured an order from Wallenius Wilhelmsen for Programmable Logic Controller (PLC) retrofit projects across 35 Pure Car and Truck Carrier (PCTC) vessels, supporting the continued reliability and operational performance of the operator’s fleet. The upgrade programme will be carried out in line with individual vessel sailing schedules and availability.

MacGregor Secures Major PCTC Retrofit Contract

Wallenius Wilhelmsen has selected MacGregor to deliver PLC retrofits across its PCTC fleet, strengthening a long-standing equipment support partnership MacGregor has secured an order from...
The Irish Coast Guard has awarded two major contracts to Zodiac Milpro for the design, construction and delivery of 38 new search and rescue vessels, representing a €14 million investment in strengthening Ireland’s maritime emergency response capability.

Irish Coast Guard Orders 38 New Rescue Boats

Zodiac Milpro will deliver 21 RHIBs and 17 Inshore Rescue Boats to the Irish Coast Guard, with the first vessels expected to enter service...
Baleària has launched its first fully electric fast ferry at Armon Shipyards in Gijón, Spain, marking a significant milestone in the development of a zero-emission maritime connection between Europe and Africa.

First Baleària Electric Fast Ferry Takes to the Water

Built by Armon Shipyards, the new fast ferry is the first of two vessels being developed for Baleària’s fully electric Strait of Gibraltar service Baleària...
Huisman has secured a contract from Siem Industries to supply knuckle boom cranes for two newbuild Offshore Support Vessels (OSVs) currently under construction at Fujian Mawei Shipbuilding in Fuzhou, China. The contract covers the delivery of 400mt and 50mt knuckle boom cranes, which will be manufactured at Huisman's production facility in Zhangzhou, Fujian Province, China.

Huisman to Supply Cranes for Siem’s Two New OSVs

Contract covers 400mt and 50mt knuckle boom cranes for Siem's two new OSVs under construction at Fujian Mawei Shipbuilding in China Huisman has secured a...

Related news