Offshore WindFloating Offshore WindDemoSATH floating offshore wind platform manufacturing moves forward in the Port of...

DemoSATH floating offshore wind platform manufacturing moves forward in the Port of Bilbao

  • Saitec Offshore has successfully completed assembly operations of the precast elements of DemoSATH hull.
  • The lifting, turning, and positioning operation of the segments has been carried out for their final assembly.
  • Set up in partnership with RWE Renewables, the project is due to be installed on BiMEP open sea test area (Biscay, Spain) in the third quarter of 2022.
Imagen que contiene vehículo militar, viejo, cubierto, sucio

Descripción generada automáticamente
DemoSATH lifting and pivoting operation

DemoSATH manufacturing works speeds up in the Port of Bilbao (Spain). The latest milestone has been the handling operation of the prototype. This consists on lifting, pivoting, and positioning the 6 precast elements that have initially been prefabricated. These elements compose the floaters of the platform and include 4 conical elements (2 per floater) and 2-cylinder elements (1 per floater).

Un barco en el agua

Descripción generada automáticamente
SATH floaters

DemoSATH prototype consists of two hulls, each having three prefabricated segments. The positioning and pivoting maneuver of these pieces has been carried out using two cranes with capacities of up to 500 tons. These cranes have raised the pieces 14 meters high and have transported 150 meters away to the specific construction supports at the foundation slab that has been specifically designed and constructed for this purpose. It is remarkable that the floater positioning results had an error below 1 centimeter.

Beginning in November 2020, DemoSATH construction and assembly works have been led by Ferrovial, world’s leading infrastructure operator. Since then, the main milestones of the project include the construction site preparation, intensive campaigns on the dosage of concrete to suit the design requirements, and the completion of the first precast phase, which includes the complete execution of the floats.

DemoSATH precast elements

The next phase involves the full assembly of the prototype and the execution of the rest of the elements of the platform. At the same time, new precast phases and movements of large components will be done, such as the installation of the tower and the wind turbine.

In this joint pilot project called DemoSATH, Saitec Offshore Technologies and RWE Renewables will test SATH floating platform in which will be mounted a 2MW wind turbine. The base of the structure will be approximately 30 metres wide and 64 metres long. The platform will be towed to its anchorage point in a test field (BiMEP) 2 miles off the Basque coast (Spain) where the sea is about 85 metres deep. DemoSATH will have the potential to produce electricity for 2,000 homes.

This project aims to collect data and gain real-life knowledge from the construction procedure, operation, and maintenance of DemoSATH floating wind platform.

Latest News

Multraship, on behalf of Rijkswaterstaat, handed over the new patrol vessel ENFORCER to the Netherlands Coastguard today. The 53-metre-long vessel will be deployed in the years ahead to safeguard the continuity of coastguard activities in the North Sea, providing additional support until the new generation of coastguard vessels goes into service.

ENFORCER Joins Netherlands Coastguard

Multraship-owned ENFORCER will strengthen Coastguard patrol and enforcement capability under the operational command of the Netherlands Coastguard Multraship has handed over the new 53-metre patrol...
Yakamoz Joint Venture has expanded its tug and mooring operations across Türkiye with the commencement of services in the Aliağa 2 service area.

Yakamoz JV Rapid Expansion of Turkish Tug Operations

Joint Venture’s 46-vessel fleet now supports tug and mooring services across four key Turkish service areas. Yakamoz Joint Venture has expanded its tug and mooring...
Chartwell Marine’s new ferry design for Newfoundland-based operator SPM Ferries has entered construction following the successful keel laying of the vessel at AISTER’s shipyard in Spain.

Keel Laid for New Saint-Pierre and Miquelon Ferry

AISTER begins construction of Chartwell Marine’s new ferry designed for SPM Ferries’ Saint-Pierre & Miquelon ferry service Chartwell Marine’s new ferry design for Newfoundland-based operator...
Steerprop has been selected to supply the complete main propulsion package for a new icebreaker being built for the Swedish Maritime Administration by HD Hyundai Heavy Industries in Ulsan, South Korea.

Steerprop Secures Major Icebreaker Propulsion Contract

Steerprop brings proven contra-rotating propeller technology to a new generation of high-performance Swedish icebreakers Steerprop has been selected to supply the complete main propulsion package...

Related news