DemoSATH floating unit launched into water

Saitec Offshore Technologies and RWE achieved another milestone in the DemoSATH project with the successful completion of the launching operation of the floating unit. The project moves forward at a fast pace for its installation later this summer. During the next months the submarine dynamic cable will be deployed at the installation site and the floater will be towed out to be connected to it, as well as to the mooring lines that were previously installed in late April.

The load out and launching operations were performed at Punta Sollana quay, in the Port of Bilbao (Spain), where the prestressed concrete platform was previously constructed and assembled, and equipped with a 2 MW turbine.

Firstly, the DemoSATH unit was loaded onto the semisubmersible barge’s deck by means of Self-Propelled Modular Transporters. The barge was then ballasted down lower into the water until the DemoSATH unit became buoyant, after which it was towed off.

DemoSATH launched in the Port of Bilbao

Araceli Martínez, Chief of Engineering at Saitec Offshore Technologies: “This is a great step forward for the DemoSATH project. The load-out and float-off operations were an important milestone to fulfill as they were the first of their kind executed for the SATH floating offshore wind turbine. The operations were thoroughly planned between all the parties involved and the final performance was excellent. Once afloat, it took less than 45 minutes to safely berth the DemoSATH wind turbine at quay. After the successful completion of the launching in the Port of Bilbao, we are proud to announce that the demonstrator is ready to become the first floating wind turbine to be commissioned to the mainland Spanish Grid during the next months.”

Martin Dörnhöfer, Director of Floating Wind at RWE Renewables: “We are glad to see DemoSATH has been launched safely and successfully. This is another important milestone towards the offshore commissioning of the floating turbine later this year. For us at RWE it is also another milestone on our way to unlock the great potential of floating wind globally, especially in countries with deeper coastal waters, like the US, France, UK, Norway and – certainly – Spain. We aim to have one gigawatt of floating wind capacity in construction or operation by 2030. Jointly with our other pilot projects, DemoSATH enables us to gain early experience for our future developments. Its innovative concrete-based platform further broadens our knowledge on innovative floating wind concepts.”

Teresa Ribera, Third Vice-President of the Government of Spain and Minister for Ecological Transition and Demographic Challenge, participated in the event and highlighted: “These companies have shown a pioneering spirit to develop this project and prove this technology. We now want to work with companies like this to help them take it forward and make floating wind a reality.”

Saitec Offshore Technologies and RWE Renewables entered into the partnership to develop DemoSATH project in 2020. The 2MW unit using SATH Technology will be installed in a test field (BIMEP) which is two miles off the Basque coast, where the sea is 85 meters deep. The SATH design allows the pre-fabrication of concrete components and uses a single-point-of-mooring system that allows the structure to yaw around its mooring and passively align itself to the wave and current direction. The aim of this demonstrator project is to test the technology for its industrialisation for offshore wind farms in deep waters.

Latest News

Inland and Coastal Marina Systems has supplied three heavy-duty concrete tug berth pontoons for the modernisation of the Tidal Basin at HM Naval Base Portsmouth, replacing ageing berthing infrastructure that had been in service for more than 40 years.

New Tug Berths for Portsmouth Naval Base

Three purpose-designed pontoons form part of a wider berthing upgrade delivered for KBS Maritime at HM Naval Base Portsmouth Inland and Coastal Marina Systems has...
SAFE Boats International, a US manufacturer of high-performance aluminium vessels for military, law enforcement and emergency response operations, has secured a five-year Blanket Purchase Agreement (BPA) valued at up to $36.4 million to support U.S. Southern Command (SOUTHCOM) Foreign Military Sales (FMS) programmes.

SAFE Boats Secures $36.4 Million Patrol Vessel Agreement

Five-year agreement will support US Foreign Military Sales programmes, with initial patrol vessel deliveries to four Caribbean nations scheduled from 2027 SAFE Boats International has...
Hydrex carried out temporary hull repairs on a 67-metre shallow-water barge during June, adapting its original repair plan to overcome challenging weather and sea conditions while maintaining safe working practices. The work was undertaken while the barge was in the Norderney and Delfzijl areas, with damage identified in void tanks 4 and 6.

Hydrex Adapts Repair Strategy for Barge Hull Repairs

Challenging sea conditions prompt Hydrex to adopt an alternative repair method for damaged sections of a barge hull Hydrex carried out temporary hull repairs on...
Damen Shipyards Group has placed a new order with EST-Floattech for two Octopus Series battery systems for installation aboard Damen Combi Freighter (CF) 3850 vessels, renewing the framework agreement between the two companies.

Damen Orders Two More Octopus Battery Systems

Damen Shipyards Group has renewed its framework agreement with EST-Floattech, ordering two Octopus Series battery systems for its Combi Freighter 3850 Damen Shipyards Group...

Related news