Renewable EnergyOffshore WindFinal wind turbine installed at Scotland’s largest offshore wind farm

Final wind turbine installed at Scotland’s largest offshore wind farm

Seagreen Wind Farm, a joint venture between SSE Renewables and TotalEnergies, achieved another landmark this week as the 114th and final wind turbine was installed.

76 of the 114 Vestas V164-10.0 MW turbines are now energised at the site, which is located 27km from the Angus coast, now producing more than two thirds of Seagreen’s full capacity power to the grid.

Once fully operational, Seagreen will be Scotland’s largest offshore wind farm and will be capable of generating around 5,000GWh of renewable energy annually – enough clean and sustainable electricity to power more than 1.6m UK homes.

The installation of the final wind turbine is yet another milestone reached in the Seagreen project in recent months. It follows on from the completion of the successful turbine foundation jacket installation campaign which included the installation of the world’s deepest wind turbine foundation at 58.6 metres.

“This latest project milestone further underlines the hard work by everyone involved in the project. The teams, including Vestas, operator of the Orca, Cadeler and our wind turbine marshalling team at Port of Nigg should be proud of what they have achieved. We will now continue with the commissioning of the final turbines and progress with the inter array cabling works.

The project has already brought benefits to the local community, the UK supply chain and once fully operational in summer 2023, it will make a significant contribution to Scotland’s and the UK’s net zero targets.”

John Hill, Seagreen’s Project Director SSE Renewables

SSE Renewables continues to lead the development and construction of the Seagreen project and will operate Seagreen on completion for the wind farm’s expected 25-year lifetime.

Latest News

Norwegian ferry operator Rødne Trafikk has taken delivery of the new all-electric car and passenger ferry Rygerlys from Oma Baatbyggeri AS in Stord. The 46-metre all-electric combi-catamaran will operate on the Lauvik–Lysebotn route under a 10-year contract with Kolumbus.

Oma Delivers All-Electric Ferry ‘Rygerlys’ to Rødne

New Oma Baatbyggeri-built electric ferry combines vehicle, passenger and cargo capacity with zero-emission propulsion Norwegian ferry operator Rødne Trafikk has taken delivery of the new...
Cochin Shipyard Limited (CSL) and Svitzer have marked the start of construction of four advanced battery-electric tugs with a formal steel-cutting ceremony at CSL’s shipyard in India. The vessels are part of a series of four next-generation TRAnsverse 2600e battery-electric tugs being built by CSL for Svitzer under a shipbuilding agreement signed in December 2025.

Cochin Begins Construction of Svitzer’s Electric Tugs

Cochin Shipyard steel-cutting ceremony marks start of four TRAnsverse 2600e battery-electric tugs for Svitzer Cochin Shipyard Limited (CSL) and Svitzer have marked the start of...
TotalEnergies Lubmarine Launches Aurelia FE, an Innovative Fuel Economy Lubricant for 4-Stroke Medium Speed Marine Engines

TotalEnergies Lubmarine Claims 1.5% Fuel Saving With New Engine Oil

TotalEnergies Lubmarine Launches Aurelia FE, an Innovative Fuel Economy Lubricant for 4-Stroke Medium Speed Marine Engines TotalEnergies Lubmarine has launched Aurelia FE, a new trunk...
Icelandic tech company Hefring Marine has been selected as one of just 15 companies to advance to Mission Track of NATO's Defence Innovation Accelerator for the North Atlantic (DIANA), from a 2026 cohort of 150 innovators selected from more than 3,600 proposals across the Alliance.

Hefring Marine Advances to NATO DIANA Mission Track

The Reykjavík-based maritime technology company is the only Icelandic firm ever to reach the programme’s Mission Track, moving its maritime intelligence technology closer to...

Related news