Ship & Boat BuildingService Operation VesselsFirst milestone in the Windea Leibniz project completed

First milestone in the Windea Leibniz project completed

The SOV Windea Leibniz is currently at Ulstein Verft for an upgrade to widen her operational scope in offshore wind. The first milestone has now been completed.

Completion of the installation of the adjustable pedestal on the Windea Leibniz.
Completion of the installation of the adjustable pedestal on the Windea Leibniz.

INSTALLATION OF ADJUSTABLE PEDESTAL

On 30 November, the yard installed the adjustable pedestal for the gangway, a lift of approx. 32 tonnes. With this pedestal in place, the vessel will be able to take on assignments on all wind farms in the North Sea, and this is the first major milestone in this project.

NEXT MILESTONE – THE CABINS

The next milestone will be to complete a 50 per cent increase in single cabins for charterers. When this milestone is completed, the vessel will have her status changed from being an SOV to becoming a CSOV.

“After the upgrade, this will be one of very few vessels with 60 single cabins for charterers, compared to the current 40. This means we can take in more people, enabling the vessel to operate as a Construction-SOV,” says Matthias Müller at Bernhard Schulte Offshore.

X-BOW AND X-STERN VESSEL

Windea Leibniz is X-BOW vessel number 100, and she also comes with the X-STERN, a design feature which Bernhard Schulte Offshore was the first shipowner to opt for. The sea trial film from the first X-STERN real-life test can be watched in the story below.

Latest News

Svitzer has signed a contract with Cheoy Lee Shipyards for the construction of six additional 29-metre TRAnsverse 2900 tugs, expanding the towage operator’s investment in its next-generation tug fleet. The contract award comes as the first of the TRAnsverse 2900 builds with Cheoy Lee undergoes final stages of construction ahead of sea trials in Zhuhai, China.

Svitzer Orders Six More TRAnsverse Tugs From Cheoy Lee

Six 29-metre TRAnsverse 2900 tugs will be delivered from early 2028, bringing the total on order with Cheoy Lee to 14 and Svitzer’s global...
Everllence has signed a framework agreement with Dutch shipbuilder Damen Shipyards Group for the serial supply of its 175D high-speed engines for Damen’s tug-building programme.

Everllence to Supply 175D Engines for Damen Tugs

Framework agreement covers long-term serial supply of Everllence 175D high-speed engines for Damen’s Fuel Flexible tug programme Everllence has signed a framework agreement with Dutch...
Norwegian ferry operator Rødne Trafikk has taken delivery of the new all-electric car and passenger ferry Rygerlys from Oma Baatbyggeri AS in Stord. The 46-metre all-electric combi-catamaran will operate on the Lauvik–Lysebotn route under a 10-year contract with Kolumbus.

Oma Delivers All-Electric Ferry ‘Rygerlys’ to Rødne

New Oma Baatbyggeri-built electric ferry combines vehicle, passenger and cargo capacity with zero-emission propulsion Norwegian ferry operator Rødne Trafikk has taken delivery of the new...
Cochin Shipyard Limited (CSL) and Svitzer have marked the start of construction of four advanced battery-electric tugs with a formal steel-cutting ceremony at CSL’s shipyard in India. The vessels are part of a series of four next-generation TRAnsverse 2600e battery-electric tugs being built by CSL for Svitzer under a shipbuilding agreement signed in December 2025.

Cochin Begins Construction of Svitzer’s Electric Tugs

Cochin Shipyard steel-cutting ceremony marks start of four TRAnsverse 2600e battery-electric tugs for Svitzer Cochin Shipyard Limited (CSL) and Svitzer have marked the start of...

Related news