Renewable EnergyOffshore WindJan De Nul completes installation of all wind turbines at TPC Offshore...

Jan De Nul completes installation of all wind turbines at TPC Offshore Wind Farm

Jan De Nul Group completed the installation of all 21 offshore wind turbines for the 109.2 MW Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration, including the installation of all subsea cables. The project teams of Jan De Nul and Hitachi now proceed with the termination and commissioning process of the complete offshore wind farm.

The project was kicked off in September 2018 with the preparatory onshore cable works. On 12 June 2021, Jan De Nul’s Offshore Jack-Up Installation Vessel Taillevent successfully completed the installation of the last 5.2 MW Hitachi wind turbine for Taiwan Power Company (TPC).

Jan Kop, Project Director TPC Project for Jan De Nul Group: “With this major milestone we have now reached the final stretch of the project which has challenged us in many ways, not even imaginable when we started more than three years ago. The COVID-19 restrictions and regulations implemented by authorities in Taiwan and around the globe have affected the project, but we have always continued with great commitment finalizing the installation of the cables, jacket foundations and wind turbines. We thank our on- and offshore teams for the great teamwork.”

Wind turbines with a downwind rotor

The TPC Offshore Wind Farm near Fangyuan, 8 kilometres off the West coast of Taiwan, is constructed in a region where typhoons are very common.

Each 5.2 MW wind turbine is installed on a jacket foundation with transition piece, anchored to the seabed using four steel pin piles, and equipped with wind turbines with a downwind rotor.

Consortium partner Hitachi Ltd. pioneered this design by obtaining the Wind Turbine Class T certification, an international standard on wind-resistant design recognising the need in regions subject to frequent typhoons.

Construction of Taiwan’s first state-owned offshore wind farm

Jan De Nul kicked off the construction works in September 2018 with the preparatory onshore cable duct installation works to connect the existing onshore substation to the cable interface near shore.

Fabrication of the different foundation components was initiated in 2019. The first foundations left the South Korean fabrication yards in April 2020 to the offshore wind farm site in Taiwan.

In June 2020, Jan De Nul installed the first pin piles and connected the first export cable to shore. By early August of that same year, the very first jacket foundation was installed and anchored to the seabed. And on 15 September the first wind turbine was erected.

Consortium Jan De Nul-Hitachi

The ‘Offshore Windfarm Phase 1 Project – Demonstration’ was awarded to the Consortium Jan De Nul – Hitachi in February 2018.

Jan De Nul Group is responsible for the design, fabrication and installation of the foundations, the provision of the offshore vessel for the installation of the wind turbines, the supply and installation of the cables off- and onshore as well as upgrading an electrical substation. Hitachi Ltd. is in charge of manufacturing, assembly, installation and other works related to the offshore wind turbines with downwind rotor.

Subsequently, the Consortium is responsible for the operation and maintenance (O&M) of the offshore wind farm over five years.

“The project has challenged us in many ways, but we have always continued with great commitment finalizing the installation. We thank our on- and offshore teams for the great teamwork.” says Jan Kop, Project Director TPC Offshore Wind Farm at Jan De Nul Group

Categories:

Latest News

Siem Industries has placed an order with China’s Fujian Mawei Shipbuilding for two Offshore Subsea Construction Vessels (OSCVs), strengthening its presence in the offshore subsea sector.

Siem Orders Two Offshore Subsea Construction Vessels

Fujian Mawei Shipbuilding will construct the two specialised Offshore Subsea Construction Vessels to a design developed in collaboration with Sirius Design & Integration and...
CBED has expanded its offshore wind support fleet with the acquisition of the Commissioning Service Operation Vessel (CSOV) Wind Dedication, formerly Seaway Moxie, from international offshore wind contractor Seaway7.

CBED Acquires CSOV from Seaway7

The newly acquired CSOV becomes the fourth vessel in CBED’s fleet, strengthening its offshore wind support capabilities CBED has expanded its offshore wind support fleet...
Safehaven Marine has signed a contract with Montevideo-based pilotage operator NEWLAR S.A. for the construction of an 18m Interceptor 60 Pilot vessel, marking the companies’ second newbuild agreement.

Safehaven Marine Wins Uruguay Pilot Boat Order

The contract will mark Safehaven Marine’s sixth Interceptor 60 Pilot and its 70th pilot boat delivered worldwide Safehaven Marine has signed a newbuild contract with...
MEYER RE has secured a contract to modernise the propulsion system of Frisia I, an island ferry operated by German ferry company AG Reederei Norden-Frisia, converting the vessel to hybrid propulsion. The contract was signed in Norddeich, Germany, on 22 October 2026.

MEYER RE Secures ‘Frisia I’ Hybrid Conversion

MEYER RE will upgrade 'Frisia I' with hybrid propulsion technology, targeting annual CO₂ emission reductions of up to 400 tonnes MEYER RE has secured a...

Related news