Launch and Recovery procedure for utility scale tidal powerplant Dragon 12 verified

Minesto, leading ocean energy developer, has successfully executed the Launch & Recovery method (LARS) for the first megawatt tidal kite Dragon 12 (1.2 MW, 25 tons). The operations developed for the Dragon 4 (100kW, 2.5 tons) were proven equally effective with the large-scale kites utilizing the same small work vessel.

The commissioning of the Launch and Recovery System (LARS) of the Dragon 12 has today been successfully completed. The scale-up of the powerplant has not required changes in the smaller Dragon 4 kite operation for launch and recovery when applied to the Dragon 12. The D12 is ten times heavier, three times larger, uses a longer tether and is installed at larger water depth. These changes in the kite parameters proved to be fully manageable with the existing LARS method, thus verifying both technical method and assessments of operating costs.

“By efficiently launching and recovering the Dragon 12 for the first time, we have now verified the critical Launch and Recovery System. It is satisfactory that the smaller kite operations are proven effective also with large-scale kites”, said Dr Martin Edlund, CEO of Minesto.

The launch and recovery were respectively done in less than 2 hours elapsed time.

”A complete run-through of the launch and recovery of the Dragon 12 powerplant over the last 24h has successfully verified the core marine operations of our kite-based power plants. This is a truly unique procedure at the core of our competitive LCOE-levels”, said Martin Edlund.

The commissioning of the Dragon 12 continues at site leading to the goal of electricity production.  Operations of the smaller Dragon 4 power-plants will continue in parallel.

Latest News

Turkish specialised commercial workboat builder Nova Shipyard has signed a contract with Italian ferry operator Navigazione Libera del Golfo (NLG S.p.A.) for the construction of a new 52-metre aluminium high-speed passenger vessel.

Nova Shipyard to Build 52m High-Speed Vessel for NLG

Aluminium passenger vessel designed by M2Engineers will provide high-capacity passenger transport across NLG’s Italian routes Turkish specialised commercial workboat builder Nova Shipyard has signed a...
From emergency hull damage in Southeast Asia to precision propeller work in Northern Europe and complex structural repairs in West Africa, the past few months have once again demonstrated the global reach and versatility of Hydrex’s underwater repair teams.

From Panama to Vietnam: Hydrex Underwater Repairs in Action Worldwide

Underwater repair projects across Europe, Asia and Africa help operators avoid drydocking and minimise downtime From emergency hull damage in Southeast Asia to precision propeller...
Damen has held a launching and naming ceremony for the Fast Crew Supplier (FCS) 2710 Tumar, built for the Ministry of Emergency Situations of the Republic of Kazakhstan.

Damen Launches ‘Tumar’ for Kazakhstan Emergency Services

New Tumar will provide Kazakhstan with a multi-role platform for emergency response and critical infrastructure protection Damen has held a launching and naming ceremony for...
Marine and engineering consultancy Global Maritime Consultancy has secured a contract from Colombo Dockyard PLC to provide Dynamic Positioning (DP) consultancy services for Next-Generation Cable Maintenance Vessels

Global Maritime Wins Cable Vessels DP Contract

Global Maritime consultancy package covers Dynamic Positioning (DP) systems, battery safety and cyber resilience for next-generation cable vessels Marine and engineering consultancy Global Maritime Consultancy...

Related news