Offshore WindFloating Offshore WindMammoet completes load-out of five floating wind platforms for the Kincardine Offshore...

Mammoet completes load-out of five floating wind platforms for the Kincardine Offshore Wind Farm

Mammoet has successfully completed the load-outs of five floating wind platforms at the Navantia Fene Shipyard in Spain. The platforms will form part of the largest floating offshore wind farm in the world, Kincardine Offshore Wind Farm.

Having previously delivered similar load-out operations at the Navantia Fene Shipyard, Mammoet had existing knowledge of the quay and was awarded the contract for the load-out of the five floating foundations. The floating offshore wind market is currently experiencing large growth, and the success of these five operations demonstrates how Mammoet can support this growth.

Considering the platforms’ weights, the surface conditions on the quay were of paramount importance. To minimize operational risk, Mammoet prepared the quay by installing hundreds of steel plates to level the surface in places where it had previously been uneven.

Furthermore, coordinating with various stakeholder groups flexibly was also required to execute each operation on schedule. This included organizing each operation to meet the appropriate tide levels and weather conditions and marrying these with the availability of the specialist seagoing vessel contractor and Navantia Fene Shipyard.

Once the quay was prepared and the specialist seagoing vessel docked, Mammoet had only a short window in which it could execute each operation. Mobilizing 100 axle lines of SPMTs split between the three columns of the triangular footprint, the floating foundation was loaded onto the three sets of SPMTs, transferred 100m across the quay, and transversely loaded onto the vessel using 54m of RoRo ramps. Once unloaded and stabilized using sea-fastening equipment, the load-out was complete. Mammoet successfully completed this operation five times over several months. 

“Having worked at this quay before doing similar complex operations, it was the key factor to deliver the floating wind platforms successfully on time”, explains Mammoet Spain Sales Manager, Javier De Pablo Arenzana. He continues: “In addition to our pool of resources and equipment, this meant we were able to offer our client a high degree of flexibility in terms of the project schedule.”

“We believe these capabilities make us well-suited to supporting the growth of the offshore floating wind sector,” he concludes.

Latest News

Dutch shipbuilder Next Generation Shipyards has announced a newbuild project for the Pacific Pilotage Authority of Canada, with the yard set to construct a new 25.5-metre pilot vessel for operations in the northern waters off Canada’s west coast. Based on a Camarc Design 25.5-metre pilot boat design, the vessel is being developed to provide reliable and dependable pilotage services in the demanding conditions of the region.

Pacific Pilotage Authority Orders New 25.5m Pilot Vessel

Next Generation Shipyards prepares to build a new Camarc-designed pilot vessel for Canada’s Pacific Pilotage Authority Dutch shipbuilder Next Generation Shipyards has announced a newbuild...
Multraship, on behalf of Rijkswaterstaat, handed over the new patrol vessel ENFORCER to the Netherlands Coastguard today. The 53-metre-long vessel will be deployed in the years ahead to safeguard the continuity of coastguard activities in the North Sea, providing additional support until the new generation of coastguard vessels goes into service.

ENFORCER Joins Netherlands Coastguard

Multraship-owned ENFORCER will strengthen Coastguard patrol and enforcement capability under the operational command of the Netherlands Coastguard Multraship has handed over the new 53-metre patrol...
Yakamoz Joint Venture has expanded its tug and mooring operations across Türkiye with the commencement of services in the Aliağa 2 service area.

Yakamoz JV Rapid Expansion of Turkish Tug Operations

Joint Venture’s 46-vessel fleet now supports tug and mooring services across four key Turkish service areas. Yakamoz Joint Venture has expanded its tug and mooring...
Chartwell Marine’s new ferry design for Newfoundland-based operator SPM Ferries has entered construction following the successful keel laying of the vessel at AISTER’s shipyard in Spain.

Keel Laid for New Saint-Pierre and Miquelon Ferry

AISTER begins construction of Chartwell Marine’s new ferry designed for SPM Ferries’ Saint-Pierre & Miquelon ferry service Chartwell Marine’s new ferry design for Newfoundland-based operator...

Related news