Triton Knoll Offshore Wind Farm Reaches Halfway Milestone

Triton Knoll has achieved another major project milestone having now installed 45 of the 90 turbines planned for the offshore array. The first of Triton Knoll’s 9.5 megawatts (MW) turbines was installed in January 2021 and the project remains on track to complete offshore construction by the end of the year. Turbine commissioning will continue through 2021, with final project completion set for early 2022.

Julian Garnsey, project director for RWE and Triton Knoll, said: “Reaching the halfway stage in our turbine installation campaign is a massive achievement for the project team, especially given the challenges encountered due to the Coronavirus pandemic. Turbine installation is continuing as planned, and this milestone is a huge step towards project completion and Triton Knoll providing clean, green renewable energy for up to 800,000 homes.”

Vestas is manufacturing the v164-9.5 MW turbines – amongst the most powerful in the world – at its Isle of Wight and Fawley facilities. Prior to installation, the blades, nacelles and tower sections are prepared for offshore use at Able Seaton Port. DEME, Triton Knoll’s installation partner, is using the jack-up vessel ‘Wind Osprey’ to install the turbines.

Once fully operational, the wind farm, which is located over 32km off the Lincolnshire coast, will be capable of making an important contribution to the UK’s net-zero targets by helping to decarbonise its energy infrastructure and powering UK homes with clean, offshore wind energy.

The project is jointly owned by RWE, J-Power and Kansai Electric Power. RWE is managing the construction, long-term operation and maintenance works on behalf of its project partners. Triton Knoll represents an investment of around £2 billion in renewable energy infrastructure with over half of that spent with the UK supply chain.

Categories:

Latest News

DBMatic, part of De Boer Marine, and Weforsea Shipping have joined forces to launch MariControl, a new maritime data technology company combining their respective expertise in vessel hardware, data infrastructure, software and digitalisation.

MariControl Launched to Simplify Vessel Digitalisation

MariControl brings DBMatic’s hardware and data infrastructure together with Weforsea Shipping’s software and maritime digitalisation expertise DBMatic, part of De Boer Marine, and Weforsea Shipping...
Robert Allan Ltd. has secured a contract to design a new RAmparts 4300 ASD tug for Guangzhou Port, China, marking the first Robert Allan Ltd.-designed tug to join the port’s fleet.

Guangzhou Port Orders RAmparts 4300 tug

New Robert Allan Ltd. designed RAmparts 4300 ASD tug to deliver approximately 92 tonnes of bollard pull for coastal towing, offshore support and anchor-handling...
Kongsberg Maritime has secured a contract to supply a fully integrated suite of technology and equipment for a new multi-purpose deepwater installation and construction vessel to be owned and operated by Solstad Offshore and SBM Offshore.

Kongsberg Maritime Secures Technology Package for New Deepwater Vessel

Comprehensive Kongsberg Maritime package combines deck machinery, dynamic positioning, propulsion and energy systems for new Solstad and SBM Offshore deepwater vessel Kongsberg Maritime has secured...
Everllence has signed a major contract with Turkish shipyard, Uzmar for 16 × 175D gensets for four Rampage 6000-DE offshore terminal tugs designed by Robert Allan Ltd. The new tugswill be operated by Smit Lamnalco, a Boskalis company, in Guyana, South America, supporting the FPSO (Floating Production Storage and Offloading) fleet operating in the Stabroek Block.

Everllence 16-Genset Contract for Smit Lamnalco Tugs

Four Rampage 6000-DE offshore terminal tugs will support Smit Lamnalco’s FPSO operations in Guyana’s Stabroek Block Everllence has signed a major contract with Turkish shipyard,...

Related news