Renewable EnergyOffshore WindVan Oord Completes 111 Monopile Installation at Baltica 2

Van Oord Completes 111 Monopile Installation at Baltica 2

Specialist vessels Svanen and Aeolus complete installation campaign delivering 107 turbine monopiles and four offshore substation foundations

Van Oord has completed the installation of all 111 monopiles for the 1.5 GW Baltica 2 offshore wind farm in Poland, marking a major milestone in one of the Baltic Sea’s most demanding offshore construction campaigns. The foundations comprise 107 monopiles for wind turbines and four for offshore substations. The installation was completed safely and on schedule, supporting the continued development of Poland’s offshore wind sector and its wider energy transition.

Baltica 2 is a 1.5 GW offshore wind farm jointly developed by PGE and Ørsted. Once operational, it will generate enough renewable electricity to power around 2.5 million Polish households, contributing significantly to Poland’s energy security and accelerating the country’s energy transition.

Ørsted is responsible for the preparation and delivery of the offshore part of the project, including the monopile installation campaign. As the main contractor for the transport and installation of the Baltica 2 foundations and scour protection, Van Oord played a central role in delivering this critical phase of construction.

Drawing on extensive experience from offshore wind projects worldwide, the Ørsted and Van Oord teams worked closely together to optimise installation sequencing, logistics and vessel deployment. This collaborative approach enabled the safe and timely installation of all 111 foundations.

The Baltica 2 monopiles are up to 100 metres long, between 9.5 and 10.5 metres in diameter, and weigh approximately 1,900 tonnes each. Their installation required close coordination across the entire supply chain, from manufacturing and transport to offshore logistics, specialist vessel operations and weather planning.

A key factor in the success of the project was the deployment of Van Oord’s specialist offshore installation vessels Svanen and Aeolus. By combining the capabilities of both vessels with extensive offshore wind expertise, Van Oord maximised installation efficiency and maintained a consistent pace of execution throughout the campaign.

The dual-vessel approach enabled multiple activities to be performed in parallel, supporting efficient offshore operations and helping to keep the project on schedule.

‘Completing the monopile installation campaign for Baltica 2 safely and on schedule is an important milestone for the project and for Poland’s offshore wind ambitions. We are proud to have contributed our offshore wind expertise, specialist vessels and experienced project teams to this complex operation. Close collaboration with Ørsted was key to maintaining momentum and delivering this phase successfully.’ – Maurits den Broeder, Managing Director Offshore Energy at Van Oord

The successful completion of the foundation installation campaign at Baltica 2 further reinforces Van Oord’s growing role in Poland’s emerging offshore wind sector. Building on its involvement in the Baltic Power offshore wind farm, the company’s first offshore wind project in Poland, Van Oord is establishing a strong track record in one of Europe’s most promising offshore wind markets.

As offshore wind deployment accelerates in the Baltic Sea, projects such as Baltic Power and Baltica 2 demonstrate Van Oord’s long-term commitment to Poland and its ambition to support the country’s energy transition through the delivery of complex offshore energy infrastructure.

Latest News

SANMAR Shipyards has delivered a new escort tug to Greek joint venture SVS, comprising Vernicos Scafi, Spanopoulos and Lyboussakis. The vessel will operate at the Port of Piraeus, supporting ship-handling and escort operations as part of SANMAR’s ongoing relationship with Med Tugs.

SANMAR Delivers Escort Tug for Port of Piraeus

The RAstar 2900SX-designed tug will provide ship-handling and escort services at the Port of Piraeus, powered by twin Caterpillar engines meeting IMO Tier III...
Diverse Marine and OEG Marine Services have signed a contract for the construction of three additional crew transfer vessels (CTVs), with deliveries scheduled throughout 2027. The vessels will be built to Diverse Marine’s BREVITY SL Class design, developed by Southampton-based naval architects Chartwell Marine. Each CTV will have an overall length of 26 metres and a load line length of less than 24 metres.

OEG Marine Services Orders Three More CTVs

The latest order adds three BREVITY SL Class CTVs to the Diverse Marine and OEG Marine Services programme, with deliveries planned across 2027 Diverse Marine...
Crowley has taken delivery of Venture, a new chartered harbour tug that will provide ship assist and escort services at the ports of Los Angeles and Long Beach, expanding the company’s operational capabilities at a major US commercial shipping gateway.

Crowley Takes Delivery of New Tug ‘Venture’

The 82-foot tug, 'Venture', built by Diversified Marine, will provide ship assist and escort services at the ports of Los Angeles and Long Beach Crowley...
Charge Offshore, part of MJR Power & Automation, is supporting Smit Terminals Europe and Smit Salvage, both part of Boskalis, with the development of a dedicated offshore charging solution as the Power2Tow project progresses through the preliminary design phase of its tender process.

Charge Offshore Monopile Charging For Power2Tow

The monopile-based system will enable Power2Tow vessels to recharge at sea, supporting lower-emission emergency towing operations in the North Sea Charge Offshore, part of MJR...

Related news