How to optimise subsea power cable routing and design

Thought Leadership – By Brian MackenzieDirector Marine Geoconsulting Europe and Africa

In today’s time-pressured and competitive offshore wind market, factors that influence the routing, design, installation and lifetime performance of power cables must be identified at an early stage to reduce installation risks and improve performance reliability. So what should we be looking out for?

Power cables are a critical yet vulnerable asset of offshore wind farms. Inter-array and export cable distances are getting longer and transporting increasing power loads, which requires extensive Geo-data to assess the operational risks and routing constraints for the cables.

Cable failure is notoriously expensive to fix, so developers strive to mitigate installation risks and ensure long-term cable performance and reliability. Putting this into practice requires a good understanding of the metocean conditions, stratigraphy, thermal properties of the soil, and geotechnical design along the cable route. But gathering data is just the start…

Build spatial flexibility into your cable route design

Cable routing is an iterative process. Developers of the grid infrastructure often make rerouting decisions during the cable design process as they receive new insights into routing constraints, or new layout opportunities come to light.

Geophysical surveys are far more spatially extensive than location-specific geotechnical investigations, which are usually executed along a planned route. If the investigated route turns out to be unviable and the revised route sends the cable through different seabed zones, leveraging existing survey data is valuable for engineering decisions. For example, our methods calibrate the existing ground-truthing data against the existing geophysical data of a larger spatial area to identify possible constraints and risks of a new route.

Subsea power cable installation

Subsea power cables being installed for a wind farm

Address landfall challenges

The coastal site investigation approach for an export cable is often challenging because of shallow water, high currents, breaking waves, and variable sea dynamics. Strong sediment mobility is common and caused by the interaction of wind, waves and sediment, which can expose the cable or progressively increase cable burial, negatively affecting its thermal behaviour.

Although a relatively small part of the power cable, the landfall presents an operational challenge for the engineering and asset lifetime. It’s beneficial to collaborate with a provider who can assess the landfall’s geological and geotechnical challenges and who can integrate the marine and terrestrial data in a single ground model as input for the cable design and installation. Therefore a provider offering a range of innovative technology and safe deployment methods is essential for acquiring Geo-data in the shallow transition zone. For example, our Rapid Airborne Multibeam Mapping System (RAMMS) delivers high-quality coastal and nearshore bathymetric datasets quickly and cost-effectively, and our WaveWalker jack-up barge is ideal for geotechnical investigations in rough surf zones. 

Fugro’s jack-up barge WaveWalker 1

WaveWalker 1, Fugro’s innovative jack-up barge for nearshore marine operations

Leveraging Geo-data and consultancy expertise

By choosing a multidisciplinary provider, developers can access a broad range of interconnected expertise ‘under one roof’. For example, our experts combine their global historical knowledge with acquired and integrated metocean, environmental, geophysical and geotechnical data into a cloud-based ground model that can be used during the design, installation and operational phases of the offshore wind farm. Understanding the implications of the data allows a multidisciplinary team to add value to site characterisation by:

  • Flagging up constraints or hazards early on
  • Identifying opportunities to optimise the cable route, saving time and money
  • Innovating – we have developed in-house cable-routing optimisation tools and machine-learning algorithms that rapidly analyse vast datasets
  • Using pioneering technology – we can measure thermal conductivity using add-on sensors incorporated into routine cone penetration test (CPT) tools
  • Assessing seabed mobility and developing models to determine the impact on cable burial and scour, and the risk of required remedial work throughout the asset lifetime
  • Proposing solutions that will prevent the need for remedial interventions during construction and subsequent operations

In conclusion…

The amount a developer can save by optimising cable route and design outweighs the cost of informed Geo-data acquisition and expert advice at the start of a project. To deliver a successful project that will stand the test of time, choose your Geo-data expert carefully and engage early on. Characterise your site; anticipate and build in sufficient flexibility for route changes; do not underestimate the landfall challenges; and leverage the Geo-data throughout the cable lifetime.

DID YOU KNOW?

– Subsea cables account for approximately 10 % of the overall CAPEX cost of developing an offshore wind farm

– Between 75 % and 80 % of insurance claims by the offshore wind industry relate to subsea

– A single power cable failure is always expensive & amounting to as much as GBP 12.5 million in corrective intervention costs and lost power generation

– The average downtime is 38 days for inter-array cable failure and 62 days for export cable failure

Latest News

LD Armateurs Group has taken delivery of the DP2 multipurpose support vessel TVO Mariner, strengthening the Group’s fleet and expanding the offshore capabilities of its subsidiary LD TravOcean, which specialises in subsea cable installation and protection.

LD Armateurs Takes Delivery of DP2 Vessel TVO Mariner

DP2 multipurpose support vessel TVO Mariner, expands LD TravOcean’s capabilities across subsea cable, telecommunications and offshore wind projects LD Armateurs Group has taken delivery of...
PaxOcean Group, a member of Kuok Maritime Group, and Ulstein Design & Solutions AS have signed a contract for the design and construction of a new ULSTEIN SX222 Service Operation Vessel (SOV) for NYK Line (Nippon Yusen Kabushiki Kaisha).

NYK Selects ULSTEIN SX222 for New Offshore Wind SOV

PaxOcean and Ulstein join forces to deliver NYK’s next-generation offshore wind SOV PaxOcean Group, a member of Kuok Maritime Group, and Ulstein Design & Solutions...
Dutch winch specialist Dijvler is expanding into the sea-going vessel market following the acquisition of the rights, designs, drawings and certifications of C-Nautical, enabling the company to launch a new standardised range of anchor and mooring winches for cargo vessels and offshore support vessels. With nearly 50 years of experience supplying anchor and mooring winches for inland waterway vessels, Dijvler is now applying its established engineering expertise to the wider commercial marine sector. The company expects to deliver its first orders for the new programme in 2027.

Dijvler Targets Sea-Going Vessels With New Winch Range

Dutch winch specialist Dijvler, builds on nearly 50 years of inland vessel experience with a new standardised range for cargo and offshore support vessels Dutch...
Safehaven Marine has launched Ederra 8, an 18-metre Interceptor 60 pilot boat built for the MVD Pilots Association in Montevideo, Uruguay. The vessel is the third pilot boat Safehaven Marine has built for the Montevideo pilots and the fourth vessel supplied to the organisation overall. The latest delivery follows the Ederra 6 and Ederra 7, two Interceptor 48 pilot boats delivered in 2022, which have been operating successfully with the pilots over recent years.

Safehaven Marine Launches Interceptor Pilot Boat Ederra-8

Safehaven Marine has launched Ederra 8, an 18-metre Interceptor 60 pilot boat built for the MVD Pilots Association in Montevideo, Uruguay https://youtu.be/a7ImyS0Er70?si=glEf4QIrKSlrVSZk Safehaven Marine has launched...

Related news