Van Oord Completes Array Cable Installation at Sofia Offshore Wind Farm

Van Oord, an international marine contractor, has successfully completed the laying, burial, termination, and testing of 109 array cables at the Sofia Offshore Wind Farm, one of the largest offshore wind projects currently under construction in the UK.

This milestone highlights Van Oord’s technical expertise in subsea cable installation and its commitment to accelerating the global energy transition through large-scale renewable energy infrastructure.

The Sofia project marked the first operational deployment of cable-laying vessel Calypso. Purpose-built to install cables for offshore wind projects worldwide, Calypso features the latest sustainable technologies and delivered a strong performance throughout its debut. Upon completion of its activities on Sofia, Calypso has immediately commenced for its next assignment. Following the cable-laying operations, the state-of-the-art Dig-It trencher, deployed from the Subsea Viking, ensured precise and efficient burial of more than 360 kilometres of cables. The ultimate cable termination and testing works were executed from several walk-to-work vessels by our experienced tower teams.

‘Completing the installation of all 109 cables is a major achievement for the Sofia project team. It reflects dedication, expertise, and close collaboration between all parties involved. I am also proud of the outstanding performance and I would like to thank all the crew and the project teams onboard the Calypso, Subsea Viking and Dig-it, and the various walk-to-work and chartered vessels for all their hard work, perseverance, and support for achieving this milestone.’- Roeland Ris, Project Director at Van Oord

About the Sofia Offshore Wind Farm

The Sofia Offshore Wind Farm is located on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK. With a capacity of 1.4 GW, it will supply power to 1.2 million UK households. Van Oord was contracted for the engineering, procurement, construction and installation (EPCI) scope for the foundations and array cables. The wind farm is expected to be fully operational in 2026. 

Latest News

OP-ED: Diesel to Electric - How Can the Maritime Industry Successfully Make the Transition?

OP-ED: Diesel to Electric – How Can the Maritime Industry Successfully Make the Transition?

Tidal Transit CEO and co-founder Leo Hambro examines the potential for electrifying commercial workboats and why the maritime industry needs to rethink its approach Marine...
Caudwell Marine expands AX300 Diesel outboard launch into Middle East

Caudwell Marine AX300 Diesel Heads for International Markets

Following its European debut at METSTRADE, the British manufacturer showcases its new commercial AX300 diesel outboard in Dubai ahead of a planned 2027 entry...
Multraship-christens-new-offshore-support-vessel-ENFORCER-for-Netherlands-Coastguard

Multraship Christens Offshore Support Vessel ENFORCER

Dutch towage and salvage specialist Multraship Towage & Salvage has christened its latest vessel, the offshore support vessel ENFORCER, during a ceremony held at...
workboat365-Robert-Allan-Ltd.-awarded-Design-Contract-for-RAstar-3200-W-and-RAstar-4200-for-SAFEEN-Drydocks

Robert Allan Ltd. Secures SAFEEN Tug Contract

SAFEEN Drydocks will construct four Robert Allan Ltd. designed RAstar 3200-W tugs and two RAstar 4200 escort tugs for deployment in demanding African operating...

Related news