Latest NewsHydrex Adapts Repair Strategy for Barge Hull Repairs

Hydrex Adapts Repair Strategy for Barge Hull Repairs

Challenging sea conditions prompt Hydrex to adopt an alternative repair method for damaged sections of a barge hull

Hydrex carried out temporary hull repairs on a 67-metre shallow-water barge during June, adapting its original repair plan to overcome challenging weather and sea conditions while maintaining safe working practices. The work was undertaken while the barge was in the Norderney and Delfzijl areas, with damage identified in void tanks 4 and 6.

The initial repair plan called for three steel doubler plates to be installed externally over the damaged sections. However, rough sea conditions prevented the safe transfer of diving equipment on board, making the planned external repair approach unfeasible.

In response, Hydrex’s technical team developed an alternative solution that allowed the work to proceed without waiting for improved weather conditions. The revised method involved carrying out the repairs internally, with three reinforced steel cofferdams installed over the damaged areas.

The adapted approach enabled Hydrex to address the hull damage while responding to the operational challenges posed by the conditions at sea.

Internal repair in void tank 4

The vessel’s crew had already installed a concrete box over the damaged area. The Hydrex technicians used this as the basis for the temporary repair and constructed a steel cofferdam on the inside of the tank, directly over the concrete box.

The cofferdam, measuring 1550 x 1915 mm, was fabricated from 8 mm steel plating. Reinforcing steel frames were welded to its outside to provide additional structural strength. All mouseholes were closed with small steel plates to make the repair completely watertight.

Once the welding had been completed, all welds were examined and approved by an independent third-party inspector using Magnetic Particle Inspection (MPI).

Two cofferdams installed in void tank 6

A similar solution was used for the two damaged areas in void tank 6. Prior to the team’s arrival, the vessel’s crew had installed two concrete boxes over these areas.

The technicians fabricated two separate steel cofferdams around the existing concrete boxes. As with the repair in void tank 4, both cofferdams were constructed using 8 mm steel plating.

The cofferdams measured 1000 x 1000 mm and 1000 x 980 mm respectively. Additional steel stiffening frames were welded onto the cofferdams to increase their strength and rigidity.

After the welding work was finished, the welds on both cofferdams were subjected to MPI and approved by an independent third-party inspector.

Adapting to the circumstances

Flexibility is essential during repair operations, especially when weather conditions make the original approach impossible to carry out safely.

For the barge, the initial plan for an external repair had to be changed because of the severe sea conditions. By switching to internally installed steel cofferdams, the team was able to provide a suitable temporary solution as a viable workaround to the planned underwater operation.

All three cofferdams were reinforced to provide a strong, watertight repair and the completed welds successfully passed independent inspection.

Latest News

The Marine Nuclear Propulsion System (MarNuPS) Pilot project has secured NOK 20 million (approximately USD 2 million) in initial funding from the Research Council of Norway, supporting the next phase of development as the consortium moves towards the physical integration and testing of a maritime nuclear propulsion system.

Nuclear Marine Propulsion Project Gains Norwegian Funding

VARD Group, Vard Electro and Island Offshore are among the partners collaborating to develop and demonstrate a new generation of nuclear-powered marine propulsion technology The...
Lifesaving equipment manufacturer LALIZAS UK, in partnership with Star International, has secured a contract to supply lifejackets to the Royal Navy, following a rigorous two-and-a-half-year procurement, evaluation and testing programme.

LALIZAS Lifejackets Selected by Royal Navy

LALIZAS UK and Star International will supply a range of lifesaving equipment following a rigorous evaluation programme led by BAE Systems Lifesaving equipment manufacturer LALIZAS...
Incat Crowther has been selected by Canadian marine transportation operator West Coast Launch to design a new fast response workboat and crew transfer vessel (CTV), following the successful operational performance of its 26-metre passenger and freight vessel Aurora.

Incat Crowther Secures New Canadian Workboat Contract

Canadian shipbuilder Bracewell Marine will construct the new Transport Canada-certified vessel, utilising Incat Crowther’s digital shipbuilding technology to support local construction and supply chain...
MAN Engines is expanding its marine propulsion portfolio with integrated POD propulsion systems for large vessels, broadening its offering and reinforcing its position as a comprehensive propulsion systems provider to the global shipbuilding industry.

MAN Engines Introduces Integrated POD Propulsion

MAN Engines combines its V12 marine engines with ZF POD drives and advanced control technology to deliver integrated propulsion solutions MAN Engines is expanding its...

Related news