Renewable EnergyOffshore WindDolWin kappa installation: Allseas strengthens position in offshore wind

DolWin kappa installation: Allseas strengthens position in offshore wind

Allseas’ Pioneering Spirit has successfully installed TenneT’s 900-megawatt DolWin kappa offshore converter station for the DolWin6 offshore grid connection system in the German North Sea.

DolWin kappa was constructed at the Dragados Offshore shipyard in Cadiz, Spain. Siemens Energy was commissioned by TenneT as general contractor to build the system.

Comprising an approximately 5,000-tonne foundation jacket and 11,000-tonne topsides housing high-voltage direct current (HVDC) technology, DolWin kappa is Allseas’ first complete platform installation for the offshore wind industry.

Completed on 4 September after a 12-day campaign, installation of DolWin kappa – including piling of jacket foundations – again demonstrates Allseas’ ability to execute technically challenging offshore projects.

Complete transport and installation solution

Designed and built by Dragados Offshore in Cádiz, Spain, DolWin kappa arrived in the Port of Rotterdam in mid-August on Allseas’ cargo barge Iron Lady. In a quick turnaround operation, all components – jacket, topsides, piles and connecting bridge – were transferred to the world’s largest construction vessel for transport to the installation site.

All components were installed directly from Pioneering Spirit, using both the topside and jacket lift systems. In another first for Allseas, the 5,000-tonne special purpose crane was deployed to drive the 10 foundation piles up to 68 metres deep into the seabed to secure the foundation jacket.

The project confirms Allseas can adapt Pioneering Spirit’s single-lift capability to provide fast and efficient transport and installation solutions for the fast-growing offshore wind market, strengthening our ambition to become a key contractor in the renewables space.

Sustainable solutions to facilitate energy transition

The installation of DolWin kappa is key to unlocking additional North Sea wind energy capacity, advancing offshore grid expansion in support of Europe’s energy security. TenneT’s DolWin6 connection will provide more than 1 million homes with renewable energy when it comes on line in 2023.

Allseas is committed to driving sustainability offshore by pioneering solutions onshore to facilitate the transition and safeguard energy affordability.

Pioneering Spirit’s size and versatility delivers high workability all year round, fast-tracking the development cycle and enabling our clients to realise their project ambitions sooner.

Creative concepts for new challenges

DolWin kappa follows substation installations end 2021 / start 2022 for the Hollandse Kust Zuid (HKZ) offshore project off the Dutch coast for German-Dutch green grid operator TenneT, and the Saint-Nazaire wind farm in France.

Allseas is also developing new concepts for the installation of next generation turbines and foundations required to meet growing demand for renewable offshore energy.

Categories:

Latest News

Svitzer has signed a contract with Cheoy Lee Shipyards for the construction of six additional 29-metre TRAnsverse 2900 tugs, expanding the towage operator’s investment in its next-generation tug fleet. The contract award comes as the first of the TRAnsverse 2900 builds with Cheoy Lee undergoes final stages of construction ahead of sea trials in Zhuhai, China.

Svitzer Orders Six More TRAnsverse Tugs From Cheoy Lee

Six 29-metre TRAnsverse 2900 tugs will be delivered from early 2028, bringing the total on order with Cheoy Lee to 14 and Svitzer’s global...
Everllence has signed a framework agreement with Dutch shipbuilder Damen Shipyards Group for the serial supply of its 175D high-speed engines for Damen’s tug-building programme.

Everllence to Supply 175D Engines for Damen Tugs

Framework agreement covers long-term serial supply of Everllence 175D high-speed engines for Damen’s Fuel Flexible tug programme Everllence has signed a framework agreement with Dutch...
Norwegian ferry operator Rødne Trafikk has taken delivery of the new all-electric car and passenger ferry Rygerlys from Oma Baatbyggeri AS in Stord. The 46-metre all-electric combi-catamaran will operate on the Lauvik–Lysebotn route under a 10-year contract with Kolumbus.

Oma Delivers All-Electric Ferry ‘Rygerlys’ to Rødne

New Oma Baatbyggeri-built electric ferry combines vehicle, passenger and cargo capacity with zero-emission propulsion Norwegian ferry operator Rødne Trafikk has taken delivery of the new...
Cochin Shipyard Limited (CSL) and Svitzer have marked the start of construction of four advanced battery-electric tugs with a formal steel-cutting ceremony at CSL’s shipyard in India. The vessels are part of a series of four next-generation TRAnsverse 2600e battery-electric tugs being built by CSL for Svitzer under a shipbuilding agreement signed in December 2025.

Cochin Begins Construction of Svitzer’s Electric Tugs

Cochin Shipyard steel-cutting ceremony marks start of four TRAnsverse 2600e battery-electric tugs for Svitzer Cochin Shipyard Limited (CSL) and Svitzer have marked the start of...

Related news