Jan De Nul completes installation of all wind turbines at TPC Offshore Wind Farm

Jan De Nul Group completed the installation of all 21 offshore wind turbines for the 109.2 MW Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration, including the installation of all subsea cables. The project teams of Jan De Nul and Hitachi now proceed with the termination and commissioning process of the complete offshore wind farm.

The project was kicked off in September 2018 with the preparatory onshore cable works. On 12 June 2021, Jan De Nul’s Offshore Jack-Up Installation Vessel Taillevent successfully completed the installation of the last 5.2 MW Hitachi wind turbine for Taiwan Power Company (TPC).

Jan Kop, Project Director TPC Project for Jan De Nul Group: “With this major milestone we have now reached the final stretch of the project which has challenged us in many ways, not even imaginable when we started more than three years ago. The COVID-19 restrictions and regulations implemented by authorities in Taiwan and around the globe have affected the project, but we have always continued with great commitment finalizing the installation of the cables, jacket foundations and wind turbines. We thank our on- and offshore teams for the great teamwork.”

Wind turbines with a downwind rotor

The TPC Offshore Wind Farm near Fangyuan, 8 kilometres off the West coast of Taiwan, is constructed in a region where typhoons are very common.

Each 5.2 MW wind turbine is installed on a jacket foundation with transition piece, anchored to the seabed using four steel pin piles, and equipped with wind turbines with a downwind rotor.

Consortium partner Hitachi Ltd. pioneered this design by obtaining the Wind Turbine Class T certification, an international standard on wind-resistant design recognising the need in regions subject to frequent typhoons.

Construction of Taiwan’s first state-owned offshore wind farm

Jan De Nul kicked off the construction works in September 2018 with the preparatory onshore cable duct installation works to connect the existing onshore substation to the cable interface near shore.

Fabrication of the different foundation components was initiated in 2019. The first foundations left the South Korean fabrication yards in April 2020 to the offshore wind farm site in Taiwan.

In June 2020, Jan De Nul installed the first pin piles and connected the first export cable to shore. By early August of that same year, the very first jacket foundation was installed and anchored to the seabed. And on 15 September the first wind turbine was erected.

Consortium Jan De Nul-Hitachi

The ‘Offshore Windfarm Phase 1 Project – Demonstration’ was awarded to the Consortium Jan De Nul – Hitachi in February 2018.

Jan De Nul Group is responsible for the design, fabrication and installation of the foundations, the provision of the offshore vessel for the installation of the wind turbines, the supply and installation of the cables off- and onshore as well as upgrading an electrical substation. Hitachi Ltd. is in charge of manufacturing, assembly, installation and other works related to the offshore wind turbines with downwind rotor.

Subsequently, the Consortium is responsible for the operation and maintenance (O&M) of the offshore wind farm over five years.

“The project has challenged us in many ways, but we have always continued with great commitment finalizing the installation. We thank our on- and offshore teams for the great teamwork.” says Jan Kop, Project Director TPC Offshore Wind Farm at Jan De Nul Group

Categories:

Latest News

Kongsberg Maritime has signed an agreement with Austal Defence Defence Australia, a subsidiary of Austal Ltd, to supply Kamewa Steel Series waterjets for the Australian Army’s new Landing Craft Medium (LCM) fleet.

Kamewa Waterjets Selected for Australian LCM fleet

Kongsberg Maritime to supply four Kamewa Steel Series waterjets for each of 18 Austal-built Landing Craft Medium vessels Kongsberg Maritime has signed an agreement with...
French shipping company Compagnie Maritime Nantaise (MN), part of the European Sogestran Group, is to build a new hybrid-powered RoRo vessel dedicated to the maritime transportation of cargoes for the space industry. The new vessel will combine conventional mechanical propulsion with wind-assisted propulsion, representing an investment in more efficient and lower-emission maritime transport for specialised cargo operations.

Compagnie Maritime Nantaise To Build Hybrid RoRo

Hybrid-powered RoRo will strengthen Compagnie Maritime Nantaise’s cargo transport capabilities for Europe’s growing space industry French shipping company Compagnie Maritime Nantaise (MN), part of the...
Grovfjord Mek. Verksted 2.0 (GMV 2.0) has signed a contract with Shetland-based Ocean Farm Services for the construction of a new aquaculture service catamaran.

GMV 2.0 to Build Workboat for Ocean Farm Services

GMV 2.0-designed 14.99m catamaran will support Ocean Farm Services’ aquaculture services in Scotland Grovfjord Mek. Verksted 2.0 (GMV 2.0) has signed a contract with Shetland-based...
inmarsat Maritime’s NexusWave, a fully managed, bonded multi-network connectivity service, has received Cyber Security Type Approval from Bureau Veritas Marine & Offshore

NexusWave gains BV cyber security approval

Bureau Veritas cyber security approval marks another milestone in Inmarsat Maritime’s drive to deliver secure and resilient maritime connectivity, supporting NexusWave deployment across global...

Related news